Ok so i figure its getting close to the project start. Hopefully it freakin warms up soon. Unless someone has a nice garage heater they can borrow me. :)
Phase one is to get the car running with the least amount of pain and money possible. Ive decided against pulling the motor at this point due to weather/time involved. Will likely do this during the summer when i can actually think without getting a brain freeze.
Phase One:
- Pull head, Pull #4 piston, Attach new Manley I Beam rod. Attach to crank with new rod bearings.
- Replace Rod Bearings for 1-3 rods to keep everything even.
- Clean up engine bay wiring. Finish install of Crane Cams Fireball Ignition. (Decided to keep the ignition, if i decide to pull it later who knows.)
- Retorque any bolt i see.
- Hook driveshaft back up.
- Verify car will start, run, and drive.
- Pull seats, and carpet. Use carpet cleaner to clean carpet and renew its original cleanliness
- Purchase and install new headunit (Just need a cheap stereo with a USB hookup)
- Repair seat tears.
- If Stephan cannot get the center console or back seat, i will be looking to puchase these along with the rest of the interior.
- Replace front fenders.
- Purchase and install Emergancy Break lever and anything missing there.
Phase Two, will be after the wedding (July 3rd). This will be where the car turns from Fun car to fun and Fast car.
- DSMLink V3 with GMMAF setup.
- 900+ cc injectors
- Large Turbo
- Built Head
- Cams
- Possible Water to Air Intercooler
- 255 Fuel Pump
- Better Exhaust
- Tune Tune Tune.
Phase one is to get the car running with the least amount of pain and money possible. Ive decided against pulling the motor at this point due to weather/time involved. Will likely do this during the summer when i can actually think without getting a brain freeze.
Phase One:
- Pull head, Pull #4 piston, Attach new Manley I Beam rod. Attach to crank with new rod bearings.
- Replace Rod Bearings for 1-3 rods to keep everything even.
- Clean up engine bay wiring. Finish install of Crane Cams Fireball Ignition. (Decided to keep the ignition, if i decide to pull it later who knows.)
- Retorque any bolt i see.
- Hook driveshaft back up.
- Verify car will start, run, and drive.
- Pull seats, and carpet. Use carpet cleaner to clean carpet and renew its original cleanliness
- Purchase and install new headunit (Just need a cheap stereo with a USB hookup)
- Repair seat tears.
- If Stephan cannot get the center console or back seat, i will be looking to puchase these along with the rest of the interior.
- Replace front fenders.
- Purchase and install Emergancy Break lever and anything missing there.
Phase Two, will be after the wedding (July 3rd). This will be where the car turns from Fun car to fun and Fast car.
- DSMLink V3 with GMMAF setup.
- 900+ cc injectors
- Large Turbo
- Built Head
- Cams
- Possible Water to Air Intercooler
- 255 Fuel Pump
- Better Exhaust
- Tune Tune Tune.